In the Edit Crane Shift dialog box, you must enter the following information In the Shift Details area:
Shift Start: Specify the shift start day (yy.mm.dd) and time (hh:mm) using the 24-hour time format.
Duration: Enter the total amount of time that the shift is on call, including activities such as breaks, which will be accounted for later. For more information on scheduling shift breaks, see Add shift activities (on page 1).
The minimum duration is 5 minutes. XPS does not create a work shift if the duration is less than the minimum.
Productivity: Enter the moves/hour value for single-cycle crane operations.
Dual Productivity: Enter the moves/hour value for double-cycle crane operations.
Twin Productivity: Enter the moves/hour value for twin crane operations.
Dual Twin Productivity: Enter the moves/hour value for twin double-cycle crane operations.
Tandem Productivity: Enter the moves/hour value for tandem crane operations.
Quad Productivity: Enter the moves/hour value for quad crane operations.
Your N4 administrator sets the productivity value for each crane. When you create a shift from scratch, this is the default shift productivity that displays in the Edit Crane Shift window. Productivity values entered for the shift override the default setting. Once the work commences, however, Quay Commander adjusts the crane plan based on real-time productivity.